EMPLOYER: RAILWAY PROJECT MANAGEMENT UNITREGION II
1. Work scope:
- Construction in in-use track
2. Main work amount:
- Excavate track bed: 22.351 m3
- Carry out dike, slope: 2.626 m3
- Remove sleeper (Concrete sleeper K1, K3A, steel sleeper, wood sleeper, prestressed concrete sleeper): 28.744 units
- Remove rail (P43, short rail, guard rail): 3.047 units
- Carry out stone track bed: 21.095 mđ
- Install sleeper (Prestressed concrete sleeper+ wood sleeper): 28.553 units
- Install rail P50 L=25m: 1.530 units
- Add ballast: 17.859 m3
3. Total contract value: 127.691.000.000 dongs
( One hundred twenty seven billions, six hundreds ninety one millions dongs)
4. Construction time:
- Start: 2009
- Complete: 2011